Thursday night, the bridge’s executive engineer Dewan. Abdul Quader has confirmed the matter.
He said work on one end of the connecting road was completed around 7 pm. Work on the road connecting Jazira ends will begin in a few days.
Meanwhile, the work of road marker is going on across the bridge.
As of Thursday, 75 per cent molding of Module-2 was done at the Mawa end of the bridge.
Work is also underway to connect 415 lampposts on the bridge.
According to the concerned sources, the work of road marking will be completed within this month. Work is underway to light the bridge on the first of June.
Work on the bridge, to be constructed at a cost of Tk 30,193 crore, started in 2014. The bridge is scheduled to open to traffic in June.